| Work resumes on bypass road By SUE WATSON Staff Writer  | Photo by Sue Watson
Getting busy
From
left, Eddie Bain, Scott Bumgardner and David Bonds with Elliott and
Britt Engineering get to work on the bypass road. Engineers shot the
center line and shoulders last week while Bain & Sons got to work
on getting the road in shape for a layer of topping. |
The North Holly Springs bypass road won’t likely be paved until next year but the remaining dirt work was begun last week. The project that was split into stages due to lack of funds several years ago. When
completed, traffic coming into Holly Springs from Highway 7 North and
Highway 4 East and Highway 311 will not have to pass through Holly
Springs directly unless motorists have business in the downtown area.
The bypass will tie into U.S. Highway 78 at the North Holly Springs
Exit. “I know the citizens are glad to get this
job going again,” said Eddie Bain with Bain & Sons Inc., a local
construction company that has the subcontract for the dirt-moving work
under prime contractor Standard Construction Co. of Memphis. Bain
& Sons will put the dirt base layer down, hopefully finishing by
Thanksgiving, Eddie Bain said. Ferrell Paving of Memphis will put down
the soil cement and paving, a job that will probably wait until next
spring. There is too much work to get the road finished this fall, Bain said. “Our
goal is to get as much done as we can before winter sets in,” he said.
“Our main thing is to stop the washing and protect what has been done.” The
washout at the Highway 178 bridge was to be fixed last week. The bridge
never was in any danger since they are sitting on concrete pilings that
go deep into the earth, Bain said. About a dump truck of dirt had
washed out due to heavy rains in September. The
county road and bridge department has been repairing the washes for the
last couple of years while the county waited for funds to let the
paving contract. “The county has been holding it together for the last two years or however long it’s been,” Bain said. County engineer Larry Britt is not optimistic that paving will get started this fall. “We
are trying to get it back ready and if the weather cooperates, they
will get some paving done,” Britt said. “If not, they will have to
shore up what they have and wait until next spring.” The
current phase of the project consists of three components – mixing soil
cement with topping material, applying an asphalt base, and then adding
the final asphalt surface, Britt said. The road has lain fallow for
about two years waiting on funding to do the paving because the project
was split up into two phases when construction materials and fuel
skyrocketed several years ago. When initial bids for the entire project
came in too high over state engineering estimates, the state ordered
the project be split into two phases with paving to be put off until
monies became available. Due to difficult
economic times which saw gasoline prices hit the $4 mark and Hurricane
Katrina which ravaged state coffers, the paving portion of the project
did not find sufficient funding until this year when the Obama
administration and Congress passed an economic stimulus package.
Federal dollars then became available this year to pave the bypass road. |