| City issues emergency order to fix sewer By SUE WATSON Staff Writer A
large sewer line pipe that is starting to separate under Falconer in
front of the fire station was the subject of an emergency order request
by John Collins, general manager of Holly Springs Utility District. The
sewer line at Falconer from Memphis to Alderson is buried about 30 feet
below ground and will not be easily dug up, Collins said during a
meeting of the mayor and board of aldermen July 1. He recommended the
board of aldermen issue an emergency order to get a company to come
clean and slipline the old pipe. A sewer line on
Chulahoma from Memphis Street to Craft is also having problems, Collins
said. Both jobs involve sliplining about 1,000 feet at a cost of $38.50
a foot or $38,500 total. “The longer we wait, the worse the problem will be to the sewer system on Falconer,” he said. He said roots were growing through drains at a residence on Chulahoma Avenue, causing sewage to back up into a residence there. Collins
said the same company that was contracted to handle the Chatham Heights
Sewer Project has agreed to take on this extra work at the same bid
price in their contract. “No contractor would bid on Falconer,” he said. “It was 30 feet deep and would cost $300 a foot.” The board issued the emergency order to take care of the sewer repairs. A process to repair collapsing sewer mains called sliplining usually requires little or no digging up of streets. A
camera is used to locate the area where pipes have separated, collapsed
or where roots have grown into the sewer main. The rubble is brought
out through a manhole. Then a slip is placed within the main, expanded
with air and chemically treated to set up and harden the slip. The
diameter of the pipe, using the slipline repair method, is slightly
smaller than the original.
|