|
Projects hit bump By SUE WATSON Staff Writer Two
projects Marshall County had in the works this legislative session in
Jackson won’t get the funding needed this year from the Mississippi
Legislature, according to consultant Gary Anderson. “It was a hectic week in the Legislature last week in bond matters,” he told the board of supervisors Monday. A
$2.5 million earmark request for the overlay of the North Holly
Springs/Highway 4 bypass hit a snag with the Legislature approving an
appropriation for only half a million dollars, he said. Anderson
said the House and Senate reached a compromise last week, trimming a
$200 million bond bill affecting economic development and road and
highway construction down to about $97 million. The
county has promoted the project in the bond bill as an economic
development project, but did not have an industry tied to it, he said. He said Governor Haley Barbour has taken a stance “if you don’t have a live fish on the hook, don’t do it.” The
Legislative session closes Saturday and must close with a balanced
budget, Anderson said, adding that a shortfall in Medicaid funding will
likely be taken up in special session after regular session. The
half-million dollars is short by about $1.5 million the total dollars
needed to overlay the bypass which will tie Highway 4 and Highway 7
north of Holly Springs into Highway 178 and U.S. 78 at the west exit. The
original cost of the 14-year-old project was estimated to run $7.4
million with the Appalachian Regional Commission putting in $4 million,
Mississippi Department of Transportation contributing $2.5 million and
the Holly Springs and county government putting in a quarter million
dollars a piece from State Aid Program funds. An additional $450,000
was to come from Holly Springs utility relocation monies. The
project ran into money trouble when the entire project was put out to
bid with all companies bidding over the estimated cost of the project,
due to a surge in oil prices in 2006-07. The state allowed the overlay
portion to be taken out of the project and and approved the
base/grade/drainage portion with expectation that monies would be
available in future years to do the overlay. But
with Toyota coming to Blue Springs and many Toyota Supplier companies
moving into North Mississippi economic development and road money was
diverted to these projects. Official reasons for
the shortfall are listed as overpasses built to cross Highway 78 and
the Burlington Northern Sante Fe Railroad rather than at grade
crossings; an shortfall of $1 million borrowed from $5 million
authorized by ARC for the project and given to West Point under the
Fordice Administration but not repaid; and rising costs of fuel and
construction materials. A March 3, 2008 cost estimate to pave the bypass road came to just over $2 million. Supervisors
expressed concern that the new road bed will deteriorate if not paved -
partly due to erosion and partly due to illegal traffic on the road and
the running of 4-wheelers up and down the slopes of the road. Not
expressing much optimism at getting easy funding, Anderson said the
county can go back to MDOT to see if any money can be found to add to
the half a million dollars. “How long can we hang on to the money?” asked District 5 supervisor Ronnie Joe Bennett. Anderson said the Legislature could sit on the bond money in the bill for another year or two. “I
am thinking, the longer it sits, the more the project will cost,” he
said. “We need $1.6 million more for overlay. Maybe we can ask MDOT for
$750,000 from its discretionary dollars and then add some local
dollars.” County administrator Larry Hall said
State Aid Project funds are harder to switch over to a project but that
the Industrial Development Authority has some bonding ability. Supervisor
George Zinn III asked if ARC has any money, but Hall reminded him that
ARC has already invested $4 million in the project. Bennett
asked whether some money set aside for an Alcohol and Drug
Rehabilitation Center could be added to the half million dollars the
state authorized for the overlay so one or the other project could be
completed. Anderson did not believe any such change in direction has much potential for success this late in the session. “They would have to ask for rule changes in the 11th hour,” he said. “And there is no guarantee the governor would sign it,” Zinn added. “There
is always danger, if you bring up a project, that it could get
everything cut out if it is brought up in a separate item,” Anderson
said. “MDOT has already put $2.5 million in the project,” said Hall. “That would be more reason not to abandon the project,” said Zinn. Anderson said the A&D Center bond money under another agency budget is not scheduled to be spent this year. Following
this discussion by the board, IDA executive director Bill Renick
obtained a signature needed from the board to finalize the Holly
Springs Commons Tax Increment Financing Plan.
|