| Red
Banks Road bridge opening soon
By SUE WATSON
Staff Writer
The Coldwater River Bridge project
will be open after the paving cures and the new construction is striped,
according to county engineer Larry Britt, who reported to the Marshall
County Board of Supervisors last week.
Paving of the approaches to the bridge
on Red Banks Road was expected to begin last week pending approval of
the mix design from the lab, Britt said. After that the area will be
striped and the bridge opened, he said.
Construction on the bridge on Highway
7 South below Waterford is scheduled to start July 9, pending the delivery
of bridge spans, according to Britt. Bridge replacement is expected
to take from four to six weeks once work begins, he said.
Supervisors discussed constructing a
detour around the two bridges on O’Dell Road in District 4 that
have been closed for about a month.
The State-Aid program that is paying
for the replacement of the two bridges will not pay for the detour,
but the board of supervisors can construct a temporary detour if there
is money in the county funds to do it, Britt said. Bids for the two
bridge replacements will be opened July 16. Construction of the O’Dell
Road bridges will likely take six months or more, depending on weather.
Overlay of a portion of Hernando Road
in District 1 won’t begin until all the paperwork is back from
State-Aid, Britt said.
Whitley Cocke made an appearance at the
June 2 board meeting to voice his appreciation for the work in the Duck
Pond Road area.
“I want to thank y’all
for what you’ve done on Duck Pond,” Cocke said. “I
thank the board of supervisors, the sheriff for patrolling Duck Pond
and Larry Hall. Y’all did a great job. The storm blew down a tree
on Atway Road and Larry Hall came out after hours and took care of it.”
IDA Report
The board signed copies of a Federal
Aviation Administration grant application for $130,000, presented to
the board by Bill Renick, director of the Industrial Development Authority.
The grant for $130,000 will be used for long-term planning and finishing
the airport fencing. The next phase of construction at the airport will
involve a runway widening project, Renick said.
In IDA’s workforce investment project,
Renick said Three Rivers Planning and Development District has awarded
$50,000 to Marshall County to continue the workforce training project
for one year. Last funding cycle, Three Rivers partnered with the county,
Rust College, and the City of Holly Springs to the level of $30,000
to fund workforce training after the Mississippi Department of Employment
Services closed its part-time office in Holly Springs.
Renick said workforce training “is
a good tool to have in the arsenal for Marshall County.”
Crisis Center Report
Gary Anderson, Kelvin Buck, David Anderson
with the State Bureau of Building and Grounds, and Paul Callens, director
of North Mississippi State Hospital in Tupelo, discussed the funding
for construction of a 16-bed Crisis Intervention Center in Marshall
County. The cost of construction of the facility has increased since
a $1.5 million bond bill was requested from the Legislature. The cost
to build the facility is now near $3.5 million, according to David Anderson.
The local delegation is likely to seek
further state bonds to finance the facility.
A separate report on this discussion
is to be published.
Elections Business
Lucy Carpenter, circuit clerk, ask the
board of supervisors to approve a raise for poll workers if the money
can be found.
Poll workers have been paid $10 an hour
for up to eight hours of training and were paid $75 a day for poll work.
Carpenter asked the board to increase
the hourly rate for training to $12 an hour and poll workers $100 or
$125 a day, depending on what the maximum pay the law provides.
“I felt $100 a day would
be enough to allow people to take off from their job to work at the
polls,” Carpenter said. “I have people who have worked a
long time (as poll workers) for not enough.”
The primary election requires about 160
poll workers to manage the 24 voting precincts in Marshall County, she
said.
Carpenter agreed that if insufficient
funds are available for the raise, she will ask poll workers to wait
until next budget year - October 1, 2007 - to be paid.
An increase from $75 to $100 a day would
cost the county an extra $4,000 and an increase to $125 would cost an
extra $8,000 to run the primary elections, Carpenter said.
Supervisor Keith Taylor motioned to pay
the maximum allowed by law if the money could be found. Supervisor Ronnie
Joe Bennett seconded. The motion passed by a unanimous vote of the board.
In other business, the board of supervisors:
-
• approved hiring Elijah Wilson to provide
probation services for the county.
-
• tabled two zoning matters that were scheduled
for public hearing.
-
• discussed the pros and cons of staying
in the state Beaver Control program.
-
• approved a 30-day extension to the tax
assessor for the final tax roll.
-
• approved claims for $275,548 in the general
fund, $304,256 in the road fund and a total claim report for June
of $611,853.
|